Calculate slabs, post holes, footings, walls, columns, bag counts, waste, and an order-ready quantity.
Project
Formula
Volume = measured area × concrete thickness. ConcreteQty converts the result to cubic yards or cubic meters, then applies waste and supplier rounding separately.
Worked example
A 12 × 10 ft slab at 4 in thick contains 1.48 yd³ before waste. With a 10% allowance and 0.25 yd³ ordering increments, the displayed order quantity is 1.75 yd³.
Assumptions
The launch defaults are 10% waste and upward rounding to 0.25 yd³ or 0.10 m³. Open “Adjust assumptions and costs” to use your supplier’s increment, actual prices, density, truck capacity, or product bag yield.
Questions
Yes. The default is 10%, and the calculated volume remains visible separately.
Yes. Add sections for slabs, footings, walls, post holes, or columns and ConcreteQty totals them.
No. It calculates quantity and purchasing estimates only.